|
Taseko Mines Limited, operators of McLeese
Lake’s Gibraltar Mine, had a very good news announcement
last week. At their first fiscal quarter of 2006 year
mark, which actually ends on the calendar date of December
31st, 2005, the mine produced 13.4 million pounds of
copper and 223,000 pounds of molybdenum.
This production produced after-tax earnings of $6.7
million, or $0.06 per share in this first quarter of
the company’s 2006 fiscal year. Taseko Mines Limited
had an operating profit of $8.1 million for the period.
Brian Bergot, the company’s Investment Relations
officer, explained that the Taseko Mines Limited currently
has three mining projects including Gibraltar Mines.
The other two are the Prosperity Copper-Gold Project
located west of Williams Lake near Fish Lake, and the
Harmony Gold Project on Queen Charlotte Island. The
company re-initiated feasibility and permitting work
on its 100 percent owned Prosperity Copper-Gold Project,
with the objective to advance the project toward a production
decision.
The Gibraltar mine met its copper production forecast
for the quarter and exceeded its molybdenum production
forecast by 11 percent. The first-quarter financial
report states revenues of $36.2 million and $5.1 million
were realised from sales of copper and molybdenum. The
average prices realised for sales were US$1.88 per pound
for copper and US$22.45 per pound for molybdenum.
Copper production was 13.4 million pounds in concentrate,
which translates to sales of 16.4 million pounds in
28,912 wet metric tonnes of concentrate.
Molybdenum production was 223,000 pounds in concentrate
and sales were 196,000 pounds in 192 wet metric tonnes
of concentrate.
A reserve update completed during the quarter resulted
in a 30 percent increase in proven and probable reserves
at Gibraltar, which was printed in the Taseko news release
late last year.
A $2 million exploration drilling program is planned
for Gibraltar in 2006 in order to more fully define
the material adjacent to existing pits with the objective
of further increasing the mineral reserves and therefore
mine life. Drilling is scheduled to begin in March.
An engineering study has been commissioned to determine
the optimum alternative for expanding mill capacity
by approximately 25 percent.
The goal is to increase revenue and reduce operating
costs by increasing metal production as a result of
higher through-puts and metal recoveries. The study
is to be completed in March. Taseko will re-assess the
economics of constructing a copper refinery at the Gibraltar
Mine site once the reserve and mill capacity studies
are completed.
Taseko
Mines Limited: Annual General Meeting, Wednesday, March
22, 2006
Click here to listen to the webcast
|