More global copper smelters were not operating in the first two months of the year than in the same period last year, mainly because of Chinese inactivity, data from satellite surveillance of metal processing plants showed.

Earth-i, which specialises in observational data, tracks smelters representing up to 90% of global production for its SAVANT service and sells data to fund managers, traders and miners.

The company said that an average of 11.5% of copper smelter capacity monitored was inactive during January and February, compared with 8.6% in the same period last year.

Inactive capacity in China rose to 8.3% from 4.8% a year earlier, with the Baotou and Kunming smelters showing as not operating.

Processing fees for copper concentrate in China have plummeted to their lowest in more than a decade owing to short supply but could recover in the second quarter when maintenance season begins, industry experts said last week.

The statement from Earth-i said there were no major developments outside of China.

“We picked up minor outages in mid-February at Australia’s Olympic Dam and Chile’s Chuquicamata,” it added.

(By Eric Onstad; Editing by David Goodman)

Disclaimer: The views expressed in this article are those of the author and may not reflect those of Kitco Metals Inc. The author has made every effort to ensure accuracy of information provided; however, neither Kitco Metals Inc. nor the author can guarantee such accuracy. This article is strictly for informational purposes only. It is not a solicitation to make any exchange in commodities, securities or other financial instruments. Kitco Metals Inc. and the author of this article do not accept culpability for losses and/ or damages arising from the use of this publication.