Indonesia, China agree $1.2 bln cost overrun for high-speed train - official

Kitco Media
By Reuters
Published:
Updated:
Reuters

JAKARTA, Feb 13 (Reuters) - Indonesia and China have agreed to a budget overrun to the tune of $1.2 billion for the first high-speed railway project in the Southeast Asian country, an Indonesian government official told parliament on Monday.

The project was previously estimated to be $2 billion over budget, raising the total cost to 113 trillion rupiah ($7.36 billion), according to the consortium of Indonesian and Chinese state companies building the railway, known as PT KCIC.

"We agreed on the cost overrun figure of $1.2 billion. There are several items that they are still reviewing regarding taxes, frequency clearing fees, but we have agreed on the numbers," said Deputy Minister of State-Owned Enterprises, Kartika Wirjoatmodjo.

Further details including an additional loan from the China Development Bank to cover the extra costs are to be finalised within a month, he added.

Companies involved in the consortium were expected to increase their equity participation, while Indonesia's state-owned railway firm PT KAI, which along with state-owned construction company Wijaya Karya controls 60% of KCIC, received a 3.2 trillion rupiah ($210.66 million) capital injection from the government last month to help complete the project.

The 142-kilometre line, which will connect the capital Jakarta with one of the country's largest cities, Bandung, was awarded to KCIC in 2015 but has faced several issues including construction delays due to the pandemic.

The project is expected to be completed in June 2023.

($1 = 15,190.0000 rupiah)

Reporting by Bernadette Christina; Editing by Kanupriya Kapoor
Disclaimer: The views expressed in this article are those of the author and may not reflect those of Kitco Metals Inc. The author has made every effort to ensure accuracy of information provided; however, neither Kitco Metals Inc. nor the author can guarantee such accuracy. This article is strictly for informational purposes only. It is not a solicitation to make any exchange in commodities, securities or other financial instruments. Kitco Metals Inc. and the author of this article do not accept culpability for losses and/ or damages arising from the use of this publication.