Kitco NEWS has a diverse team of journalists reporting on the economy, stock markets, commodities, cryptocurrencies, mining and metals with accuracy and objectivity. Our goal is to help people make informed market decisions through in-depth reporting, daily market roundups, interviews with prominent industry figures, comprehensive coverage (often exclusive) of important industry events and analyses of market-affecting developments.

Editor's Note: With so much market volatility, stay on top of daily news! Get caught up in minutes with our speedy summary of today's must-read news and expert opinions. Sign up here!

(Kitco News) - Osisko Development (TSX.V: ODV) today announced the results from its Preliminary Economic Assessment ("PEA") for the Cariboo gold project in Central British Columbia, Canada.

The company said that the study outlines total gold production of 2.8 million gold ounces, resulting in an average annual gold production profile of 236,000 ounces with an all-in sustaining cost per ounce of $1,222 (US$962).

The project's after-tax net present value (5% discount rate) is $764 million with an after-tax internal rate of return of 21.4% at a gold price of $2,223 (US$1,750) per ounce, and $912 million and 24.5% at a spot gold price for May 19, 2022 at $2,343 (US$1,845) per ounce.

The project's pre-tax payback period is 5.8 years (post-tax 6.0 years), with first gold pour targeted for Q1 2024.

The project is planned in two phases: Phase 1 is at 2,000 tpd for 2.5 years, increasing during Phase II to an average production of 8,000 tpd over a 9.5-year LOM.

The company added that this study has focused on five underground zones: Shaft Zone, Valley Zone, Cow Zone, Mosquito Zone and Lowhee Zone. The mining zones are accessed via three main portals and are connected by an internal ramp system.


Superior Gold reports lower production in Australia in Q1 due to the planned mill shutdown, maintains 2022 guidance

"The PEA illustrates potential economics for a low cost, large scale, underground gold mine, with industry leading operating costs. The company plans to proceed with a feasibility study in connection with the work plan recommended by the PEA," Osisko said in a statement.

Osisko Development is a gold development company advancing the Cariboo gold project and other Canadian and Mexican properties, with the objective of becoming the next mid-tier gold producer.

Kitco Media

Vladimir Basov

Vladimir (PhD, MEng in Mining) is a professional mining engineer, scientist and analyst that has more than 20 years of practical in-field and research experience. He is particularly interested in collecting, processing baseline data and writing insightful data-driven mining industry analytics, articles, statistical and research reports.

Mdi Earth Logo

Share

Disclaimer: The views expressed in this article are those of the author and may not reflect those of Kitco Metals Inc. The author has made every effort to ensure accuracy of information provided; however, neither Kitco Metals Inc. nor the author can guarantee such accuracy. This article is strictly for informational purposes only. It is not a solicitation to make any exchange in commodities, securities or other financial instruments. Kitco Metals Inc. and the author of this article do not accept culpability for losses and/ or damages arising from the use of this publication.