Hummingbird begins commissioning of its Kouroussa gold mine in Guinea

Kitco Media
By Vladimir Basov
Published
Updated
Kitco News
The Leading News Source in Precious Metals

Kitco NEWS has a diverse team of journalists reporting on the economy, stock markets, commodities, cryptocurrencies, mining and metals with accuracy and objectivity. Our goal is to help people make informed market decisions through in-depth reporting, daily market roundups, interviews with prominent industry figures, comprehensive coverage (often exclusive) of important industry events and analyses of market-affecting developments.

Editor noteGet all the essential market news and expert opinions in one place with our daily newsletter. Receive a comprehensive recap of the day's top stories directly to your inbox. Sign up here!

(Kitco News) - Hummingbird Resources (AIM: HUM) announced today that the Kouroussa gold mine processing plant has reached the practical completion stage, and has entered the commissioning phase towards achieving first gold pour this quarter.

The company said that pre-operational and cold commissioning is currently underway and, once completed, will move to the hot commissioning phase, followed by the first gold pour in Q2 2023.

Importantly, according to a press release, sufficient ore feed tonnes are on the ROM pad for commissioning, with mining activities accelerating to provide increased ore feed tonnes on the ROM pad for first gold pour followed by name plate production.

The Kouroussa gold mine in Guinea is a high grade, over 4 grammes per tonne, open pit operation, and is the company's second operating gold asset in West Africa.

CEO Dan Betts commented, "Kouroussa is on track to pour first gold within the current quarter, and the start of commissioning of the processing plant is a significant step forward in achieving this objective. As we begin the commissioning phase to bring Kouroussa online, we remain heavily focused on safety at this busy time.

"Additionally, operational readiness and the transition to daily operations is a key part of this phase as we look not just to first gold, but to ramping up production to name plate capacity, moving the company to being a +200,000-ounce, multi-asset, multi-jurisdiction gold producer." 

Hummingbird Resources currently has two core gold projects, the operational Yanfolila gold mine in Mali, and the Kouroussa gold mine in Guinea, which will more than double current gold production when in production, scheduled for first gold pour the end of Q2 2023.

Further, the company has a controlling interest in the Dugbe gold project in Liberia that is being developed by joint venture partners, Pasofino Gold Limited. The company said the final feasibility results on Dugbe showcase 2.76Moz in reserves and strong economics such as a 3.5-year capex payback period once in production, and a 14-year life of mine at a low AISC profile.


Fortuna Silver temporarily halts operations at its San Jose mine in Mexico due to illegal blockade

Kitco Media

Vladimir Basov

Vladimir (PhD, MEng in Mining) is a professional mining engineer, scientist and analyst that has more than 20 years of practical in-field and research experience. He is particularly interested in collecting, processing baseline data and writing insightful data-driven mining industry analytics, articles, statistical and research reports.

Mdi Earth Logo

Share

Disclaimer: The views expressed in this article are those of the author and may not reflect those of Kitco Metals Inc. The author has made every effort to ensure accuracy of information provided; however, neither Kitco Metals Inc. nor the author can guarantee such accuracy. This article is strictly for informational purposes only. It is not a solicitation to make any exchange in commodities, securities or other financial instruments. Kitco Metals Inc. and the author of this article do not accept culpability for losses and/ or damages arising from the use of this publication.